It has been a very busy few months at The Point with a lot of significant construction progress being made.

Posted by:

CA Partners Ltd.

Date:

Apr 3, 2017

Highlights include:

  • All Civil works have been completed.
  • The Lighting and Landscape design work has been completed.
  • Foundations have been cast on the North Townhouses and vertical construction is scheduled to begin in the 1st week of April.
  • Foundation of the South Townhouses will begin in the 2nd week of April and by the 1st week of May floor construction will begin.
  • The foundations and walls of Villa 1 & 2 are also underway and excavation for Villa 3 will begin next week.

Stay tuned for our next construction update in two months time.